Wednesday, February 25, 2009

Stockpiled Dirt at Heritage Park

600 North and Fairfield Road (looking north)
Dirt will be used here to fill in a portion of the hollow
on the right hand side of this picture.
A sidewalk will then be installed in this area.


This spring you will see dirt that has been stockpiled at Heritage Park removed. The City moved dirt from several different locations last year and stored it on the Heritage Park property so that it could be used for 2009 street projects. It has been estimated that this has saved the City hundreds of thousands of dollars because the City now does not need to purchase dirt for some of the street projects this year.
Some of the material will be moved to:
  • 500 East Street for culvert upgrade and roadway aligning between Crestwood Road and Oak Lane.
  • Fairfield Road for culvert extension and roadway widening between 600 North and Boynton Road.

Some of the material will remain at Heritage Park to be used for grading and a parking lot.